Name of beneficiary: Szalajka Team Kft.
Project title: ENERGY REFIT OF THE SALAJKA INCLUSIVE
Aid intensity (%): 55%
Project ID number: GINOP-4.1.4-19-2020-01341
The effective completion date of the project is 28.03.2022.
Contracted amount of aid: HUF 14.611.497
Presentation of the project content:

The purpose of the development 3348 Szilvásvárad, Egri út 2. energy modernisation of the heating system of a disused restaurant building, improving its energy efficiency by using solar energy.
The building, built in 1950, underwent major renovation in the early 2000s, is in good structural and structural condition, but has very high energy costs, so its heating system needs to be upgraded and a solar panel system installed to cover the high electricity costs.
Energy efficiency improvements are justified on the basis of energy assessments and calculations:
– Modernisation of the heating system of the building
– Installation of a solar PV system to increase the use of renewable energy for the grid electricity supply of the building to be developed only.
The entire heating system of the Szalajka Inn building will be upgraded with a new condensing gas boiler, a new piping system will be installed, heat exchangers will be replaced and thermostatic valves will be installed.
For the electricity supply system, the applicant intends to install a solar system on the roof of the building, with a capacity of 44.25 kW, connected to the grid via an inverter, in line with the current load data, for the sole purpose of supplying electricity to the economic activities in the building.